IRS/2024/4473/GENERAL
Notification details
| Status | Completed |
|---|---|
| First observed date | 11 May 2024 |
| First observed time | 14:37 |
| Installation | n/a |
| Field | BELINDA |
| Latitude | 57° 3' 6.815'' N |
| Longitude | 0° 56' 37.93'' E |
| Quadrant / block no. | 21 / 30 |
| Was the non compliance ever ongoing | No |
Inspector assessment details
| Inspector's comments | The response to the RFI provides sufficient information regarding the background and decision process which led to the non-compliance. This was a one time activity and lessons taken to mitigate the risk of reoccurence. |
|---|
Formal investigation
| Formal investigation ever opened | No |
|---|