IRS/2022/1353/OCR
Notification details
| Status | Completed |
|---|---|
| First observed date | 15 June 2022 |
| First observed time | 10:00 |
| Organisation involved | SHELL U.K. LIMITED |
| Installation | Shearwater C PUQ Platform |
| Field | SHEARWATER |
| Latitude | 57° 1' 53.0'' N |
| Longitude | 1° 57' 19.0'' E |
| Quadrant / block no. | 22 / 30 |
Breach details
| Related to a breach where an OCR permit is in place | Yes |
|---|---|
| Breached conditions | Condition 2 - use of a chemical in line with the chemical permit submission and CRA: application description, non compliance associated with 85 ppm dose rate, exceeding the pump rate of 0.21 l/h, not meeting the 23 mg/L dosage stated for the basis of CHARM, potential annual use / discharge breach TBC Release quantity estimated at 700 kg for initial notification of non compliance, quantity will be updated once confirmed by Production Chemistry Version 2 update 21/6/2022: quantity of release updated with input from Production Chemistry Version 3 update 8/7/2022: quantity of release updated with input from Production Chemistry for non compliance period Dec 2021 - end June 2022. Total release calculated as 2706.82 kg. |
| Related either wholly or partially to use and/or discharge of a chemical(s) | Yes |
Chemical 1
| Chemical product released | SCAL16662A |
|---|---|
| Total quantity of chemical used in excess of permitted quantity (kg) | 2706.82 |
| Total quantity of chemical released in excess of permitted quantity (kg) | 2706.82 |
| Related to a subsea discharge | No |
|---|---|
| Was the subsea discharge greater than 1 tonne over 12 hours | No |
| Was the non compliance ever ongoing | Yes |
Formal investigation
| Formal investigation ever opened | Yes |
|---|