Back

IRS/2024/3914/OCR

Notification details

Status Completed
First observed date 15 January 2024
First observed time 16:30
Organisation involved CHRYSAOR NORTH SEA LIMITED
Installation Armada Platform
Field FLEMING
Latitude 57° 57' 26.0'' N
Longitude 1° 50' 42.0'' E
Quadrant / block no. 22 / 05

Breach details

Related to a breach where an OCR permit is in place Yes
Breached conditions 3
Related either wholly or partially to use and/or discharge of a chemical(s) Yes

Chemical 1

Chemical product released KIRASOL-3181SC1
Total quantity of chemical used (kg) 63.6
Total quantity of chemical released (kg) 0
Related to a subsea discharge No
Was the subsea discharge greater than 1 tonne over 12 hours No
Was the non compliance ever ongoing No

Formal investigation

Formal investigation ever opened No