IRS/2024/5192/OCR
Notification details
| Status | Completed |
|---|---|
| First observed date | 18 October 2024 |
| First observed time | 16:30 |
| Organisation involved | NEO ENERGY RESOURCES UK LIMITED |
| Installation | Piper B Platform |
| Field | PIPER |
| Latitude | 58° 27' 40.86'' N |
| Longitude | 0° 15' 3.83'' E |
| Quadrant / block no. | 15 / 17 |
Breach details
| Related to a breach where an OCR permit is in place | Yes |
|---|---|
| Breached conditions | 14 |
| Related either wholly or partially to use and/or discharge of a chemical(s) | No |
| Related to a subsea discharge | No |
|---|---|
| Was the subsea discharge greater than 1 tonne over 12 hours | No |
| Was the non compliance ever ongoing | No |
Formal investigation
| Formal investigation ever opened | No |
|---|