IRS/2022/1133/OPPC

Notification details

Status Completed
First observed date 30 April 2022
First observed time 14:50
Organisation involved TOTALENERGIES E&P UK LIMITED
Installation Alwyn North NAB Platform
Field ALWYN NORTH
Latitude 60° 48' 36.0'' N
Longitude 1° 44' 7.0'' E
Quadrant / block no. 3 / 09

Breached conditions details

Related to a breach of an approved permit Yes
Breached conditions Individual OPPC non-compliance raised as OIW was above 300mg/l
Total oil discharged 0.1887 tonnes

Non-compliance details

Related to discharge limits in Table 1 Yes
Non-compliance reasons related to discharge limits in Table 1 Maximum concentration
Related to other discharge information in Table 1 No
Related to Table 2 No
Non-compliance ever ongoing Yes

Weather conditions

Wind direction 227°
Wind speed 9 knots
Significant wave height 1.3 metres

Formal investigation

Formal investigation ever opened No