Back

IRS/2026/7727/OPPC

Notification details

Status Completed
First observed date 18 May 2026
First observed time 09:10
Organisation involved SPIRIT ENERGY PRODUCTION UK LIMITED
Installation Morecambe South CPP1 Platform
Field SOUTH MORECAMBE
Latitude 53° 50' 44.31'' N
Longitude 3° 35' 0.38'' W
Quadrant / block no. 110 / 3

Breached conditions details

Related to a breach of an approved permit Yes
Breached conditions A valid sample must be taken from each discharge of produced water

Non-compliance details

Related to discharge limits in Table 1 No
Related to other discharge information in Table 1 No
Related to Table 2 Yes
Non-compliance reasons related to Table 2 Sampling and analysis method
Non-compliance ever ongoing No

Formal investigation

Formal investigation ever opened No