PON1/483
Notification details
| Status | Completed |
|---|---|
| First observed date | 09 July 2011 |
| First observed time | 13:30 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Tern Platform |
| Installation type | Fixed |
| Field | TERN |
| Latitude | 61° 16' 34.0'' N |
| Longitude | 0° 55' 10.0'' E |
| Quadrant / block no. | 210 / 25 |
Chemical 1
| Chemical product released | Brayco Micronic |
|---|---|
| Total quantity of chemical released | 50.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Failed subsea hydraulic line fitting. |
|---|