PON1/495
Notification details
| Status | Completed |
|---|---|
| First observed date | 13 July 2011 |
| First observed time | 17:05 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Harding Platform |
| Installation type | Fixed |
| Field | HARDING |
| Latitude | 59° 16' 46.24'' N |
| Longitude | 1° 30' 58.04'' E |
| Quadrant / block no. | 9 / 23 |
Chemical 1
| Chemical product released | Erifon 818 |
|---|---|
| Total quantity of chemical released | 22.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Failure of conductor tensioner hydraulic cylinder. |
|---|