PON1/683
Notification details
Status | Completed |
---|---|
First observed date | 06 October 2011 |
First observed time | 23:07 |
Incident type(s) | Chemical release |
Organisations involved | |
Installation | Ettrick FPSO Aoka Mizu |
Installation type | Fixed |
Field | ETTRICK |
Latitude | 57° 54' 2.283'' N |
Longitude | 0° 36' 30.003'' W |
Quadrant / block no. | 20 / 3 |
Chemical 1
Chemical product released | Monoethyleneglycol |
---|---|
Total quantity of chemical released | 396.0 kg |
Chemical 2
Chemical product released | Sodium Nitrate |
---|---|
Total quantity of chemical released | 15.0 kg |
Formal investigation
Formal investigation ever opened | Yes |
---|
Close off details
Release ever ongoing | No |
---|
Source details
Source | Failure of an over pressure bursting disc |
---|