PON1/692
Notification details
| Status | Completed |
|---|---|
| First observed date | 12 October 2011 |
| First observed time | 08:30 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Banff FPSO Petrojarl Banff |
| Installation type | Fixed |
| Field | BANFF |
| Latitude | 57° 0' 5.0'' N |
| Longitude | 1° 17' 39.0'' E |
| Quadrant / block no. | 29 / 2 |
Chemical 1
| Chemical product released | Pelagic 100 Production Control Fluid |
|---|---|
| Total quantity of chemical released | 11594.45 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | Yes |
|---|
Source details
| Source | Subsea Isolation Valve accumulator hydraulic fluid leak |
|---|