PON1/857
Notification details
| Status | Completed |
|---|---|
| First observed date | 24 January 2012 |
| First observed time | 19:30 |
| Incident type(s) | Oil release |
| Organisations involved | |
| Installation | Pelican Manifold |
| Installation type | Fixed |
| Field | Pelican |
| Latitude | 61° 1' 59.76'' N |
| Longitude | 1° 7' 38.11'' E |
| Quadrant / block no. | 211 / 26 |
Oil release details
| Oil product released | Crude |
|---|---|
| How was the quantity released determined | |
| Total quantity of oil released | 0.012 tonnes |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Subsea pipeline (residual oil released on disconnection) |
|---|