PON1/880
Notification details
Status | Completed |
---|---|
First observed date | 16 February 2012 |
First observed time | 23:30 |
Incident type(s) | Chemical release |
Organisations involved | |
Installation | Foinaven - FPSO Petrojarl |
Installation type | Fixed |
Field | FOINAVEN |
Latitude | 60° 18' 58.24'' N |
Longitude | 4° 16' 23.85'' W |
Quadrant / block no. | 204 / 24 |
Chemical 1
Chemical product released | RX-5227 |
---|---|
Total quantity of chemical released | 2.79 kg |
Chemical 2
Chemical product released | RX-9022 |
---|---|
Total quantity of chemical released | 0.5 kg |
Formal investigation
Formal investigation ever opened | Yes |
---|
Close off details
Release ever ongoing | No |
---|
Source details
Source | Release of chemicals during pipeline depressurining |
---|