PON1/962
Notification details
| Status | Completed |
|---|---|
| First observed date | 14 March 2012 |
| First observed time | 12:00 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Bure Subsea Completion Bure O |
| Installation type | Fixed |
| Field | |
| Latitude | 53° 5' 1.0'' N |
| Longitude | 2° 32' 50.0'' E |
| Quadrant / block no. | 49 / 28 |
Chemical 1
| Chemical product released | Aqualink HT804F v2 |
|---|---|
| Total quantity of chemical released | 10245.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Release from main subsea hydraulic supply line |
|---|