PON1/1262
Notification details
| Status | Completed |
|---|---|
| First observed date | 20 August 2012 |
| First observed time | 02:15 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Thistle A Platform |
| Installation type | Fixed |
| Field | THISTLE |
| Latitude | 61° 21' 46.93'' N |
| Longitude | 1° 34' 47.14'' E |
| Quadrant / block no. | 211 / 18 |
Chemical 1
| Chemical product released | Enviromul mud system |
|---|---|
| Total quantity of chemical released | 238.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Platform hose transferring OBM slops to supply vessel. |
|---|