PON1/10157
Notification details
Status | Completed |
---|---|
First observed date | 05 March 2021 |
First observed time | 18:00 |
Incident type(s) | Chemical release |
Organisations involved | |
Installation | GPIII subsea control system |
Installation type | Fixed |
Field | Donan |
Latitude | 58° 21' 38.6'' N |
Longitude | 0° 52' 4.69'' E |
Quadrant / block no. | 15 / 20 |
Chemical 1
Chemical product released | Castrol Transaqua HT2 |
---|---|
Total quantity of chemical released | 731.0 kg |
Formal investigation
Formal investigation ever opened | Yes |
---|
Close off details
Release ever ongoing | Yes |
---|
Source details
Source | Production - Chemicals - Subsea Valve Failure Operational Failure |
---|