IRS/2021/300/PON1
Notification details
| Status | Completed |
|---|---|
| First observed date | 14 November 2021 |
| First observed time | 01:45 |
| Incident type(s) | Chemical release |
| Organisations involved | NEO ENERGY RESOURCES UK LIMITED |
| Installation | Clyde Platform |
| Installation type | Production installation (including any connected infrastructure) |
| Field | CLYDE |
| Latitude | 56° 27' 10.0'' N |
| Longitude | 2° 17' 18.0'' E |
| Quadrant / block no. | 30 / 17 |
Chemical 1
| Chemical product released | CRW85733 |
|---|---|
| Total quantity of chemical released | 12.1 kg |
Chemical 2
| Chemical product released | MONOETHYLENE GLYCOL (MEG) (ALL DILUTIONS) |
|---|---|
| Total quantity of chemical released | 231.0 kg |
Formal investigation
| Formal investigation ever opened | No |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Cooling Medium System - Valve Failure |
|---|