IRS/2021/521/PON1
Notification details
Status | Completed |
---|---|
First observed date | 14 April 2021 |
First observed time | 16:56 |
Incident type(s) | Chemical release |
Organisations involved | PIERCE PRODUCTION COMPANY LIMITED, SHELL U.K. LIMITED |
Installation | Haewene Brim |
Installation type | Production installation (including any connected infrastructure) |
Field | PIERCE |
Latitude | 57° 9' 41.0'' N |
Longitude | 2° 17' 32.0'' E |
Quadrant / block no. | 23 / 27 |
Chemical 1
Chemical product released | Castrol Transaqua HT2 |
---|---|
Total quantity of chemical released | 742.0 kg |
Formal investigation
Formal investigation ever opened | No |
---|
Close off details
Release ever ongoing | Yes |
---|
Source details
Source | Hydraulics - Open System - Release During Operation |
---|