IRS/2022/1724/PON1
Notification details
| Status | Completed |
|---|---|
| First observed date | 05 September 2022 |
| First observed time | 14:00 |
| Incident type(s) | Chemical release |
| Organisations involved | CNR INTERNATIONAL (U.K.) LIMITED |
| Installation | Tiffany Platform |
| Installation type | Production installation (including any connected infrastructure) |
| Field | TIFFANY |
| Latitude | 58° 30' 19.184'' N |
| Longitude | 1° 15' 54.828'' E |
| Quadrant / block no. | 16 / 17 |
Chemical 1
| Chemical product released | Castrol Brayco Micronic SV/3 |
|---|---|
| Total quantity of chemical released | 8480.2 kg |
Formal investigation
| Formal investigation ever opened | No |
|---|
Close off details
| Release ever ongoing | Yes |
|---|
Source details
| Source | Hydraulics - Open System - Fittings / Connections |
|---|