IRS/2022/1839/PON1
Notification details
| Status | Completed |
|---|---|
| First observed date | 30 September 2022 |
| First observed time | 12:00 |
| Incident type(s) | Chemical release |
| Organisations involved | CHRYSAOR LIMITED |
| Installation | Lomond Platform |
| Installation type | Production installation (including any connected infrastructure) |
| Field | LOMOND |
| Latitude | 57° 17' 15.15'' N |
| Longitude | 2° 10' 41.51'' E |
| Quadrant / block no. | 23 / 21 |
Chemical 1
| Chemical product released | Oceanic HW540 E |
|---|---|
| Total quantity of chemical released | 1023.43 kg |
Formal investigation
| Formal investigation ever opened | No |
|---|
Close off details
| Release ever ongoing | Yes |
|---|
Source details
| Source | Hydraulics - Closed System - Valve Failure |
|---|