IRS/2023/2551/PON1
Notification details
| Status | Completed |
|---|---|
| First observed date | 14 March 2023 |
| First observed time | 20:15 |
| Incident type(s) | Chemical release |
| Organisations involved | TAQA BRATANI LIMITED |
| Installation | Brae A Platform |
| Installation type | Production installation (including any connected infrastructure) |
| Field | BRAE-CENTRAL [Part of BRAE] |
| Latitude | 58° 41' 33.5'' N |
| Longitude | 1° 16' 54.7'' E |
| Quadrant / block no. | 16 / 7 |
Chemical 1
| Chemical product released | Oceanic HW443ND |
|---|---|
| Total quantity of chemical released | 1093.0 kg |
Formal investigation
| Formal investigation ever opened | No |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Hydraulics - Open System - Not determined |
|---|