Back

IRS/2023/2932/PON1

Notification details

Status Completed
First observed date 17 June 2023
First observed time 16:50
Incident type(s) Oil release
Organisations involved CHRYSAOR PRODUCTION (U.K.) LIMITED
Installation Boulton Wellhead Platform
Installation type Production installation (including any connected infrastructure)
Field Boulton BM
Latitude 54° 14' 40.101'' N
Longitude 2° 9' 9.104'' E
Quadrant / block no. 44 / 21

Oil release details

Oil product released Hydraulic Oil
How was the quantity released determined Estimated using Bonn Agreement Code
Total quantity of oil released 0.000016469 tonnes

Formal investigation

Formal investigation ever opened No

Close off details

Release ever ongoing No

Source details

Source Pipework - Small Bore Fittings