IRS/2023/3139/PON1
Notification details
| Status | Completed |
|---|---|
| First observed date | 30 July 2023 |
| First observed time | 09:30 |
| Incident type(s) | Chemical release |
| Organisations involved | ITHACA ENERGY (UK) LIMITED |
| Installation | Alba Northern Platform |
| Installation type | Production installation (including any connected infrastructure) |
| Field | ALBA |
| Latitude | 58° 3' 31.77'' N |
| Longitude | 1° 4' 51.75'' E |
| Quadrant / block no. | 16 / 26 |
Chemical 1
| Chemical product released | CALCIUM CHLORIDE BRINE |
|---|---|
| Total quantity of chemical released | 164726.0 kg |
Chemical 2
| Chemical product released | Halliburton XP-07 |
|---|---|
| Total quantity of chemical released | 1.383 kg |
Formal investigation
| Formal investigation ever opened | No |
|---|
Close off details
| Release ever ongoing | Yes |
|---|
Source details
| Source | Decommissioning Related |
|---|