IRS/2023/3303/PON1
Notification details
Status | Completed |
---|---|
First observed date | 15 July 2023 |
First observed time | 00:01 |
Incident type(s) | Chemical release |
Organisations involved | ITHACA ENERGY (UK) LIMITED |
Installation | Captain WPP'A' |
Installation type | Production installation (including any connected infrastructure) |
Field | CAPTAIN |
Latitude | 58° 17' 57.0'' N |
Longitude | 1° 46' 40.0'' E |
Quadrant / block no. | 13 / 22 |
Chemical 1
Chemical product released | Oceanic HW540 E |
---|---|
Total quantity of chemical released | 5754.0 kg |
Formal investigation
Formal investigation ever opened | No |
---|
Close off details
Release ever ongoing | No |
---|
Source details
Source | Hydraulics - Closed System - Valve Failure |
---|