IRS/2023/3515/PON1
Notification details
| Status | Completed |
|---|---|
| First observed date | 25 October 2023 |
| First observed time | 14:00 |
| Incident type(s) | Chemical release |
| Organisations involved | CNR INTERNATIONAL (U.K.) LIMITED |
| Installation | Ninian Central Platform |
| Installation type | Production installation (including any connected infrastructure) |
| Field | NINIAN |
| Latitude | 60° 51' 24.0'' N |
| Longitude | 1° 28' 9.0'' E |
| Quadrant / block no. | 3 / 3 |
Chemical 1
| Chemical product released | METHANOL |
|---|---|
| Total quantity of chemical released | 5.0 kg |
Formal investigation
| Formal investigation ever opened | No |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Fixed Chemical Pipework (Production Chemicals) - Pinhole Leak |
|---|