IRS/2023/3767/PON1
Notification details
Status | Completed |
---|---|
First observed date | 12 December 2023 |
First observed time | 11:24 |
Incident type(s) | Chemical release |
Organisations involved | ENI ENERGY E&P UK LIMITED |
Installation | Cygnus B Platform |
Installation type | Production installation (including any connected infrastructure) |
Field | CYGNUS |
Latitude | 54° 35' 59.75'' N |
Longitude | 2° 11' 41.33'' E |
Quadrant / block no. | 44 / 11 |
Chemical 1
Chemical product released | Castrol Transaqua HT2 |
---|---|
Total quantity of chemical released | 87.5 kg |
Formal investigation
Formal investigation ever opened | No |
---|
Close off details
Release ever ongoing | No |
---|
Source details
Source | Hydraulic Manifold/Control Panel - Piston seal failure |
---|