Back

IRS/2025/5847/PON1

Notification details

Status Completed
First observed date 24 February 2025
First observed time 15:00
Incident type(s) Chemical release
Organisations involved PIERCE PRODUCTION COMPANY LIMITED
Installation Haewene Brim
Installation type Production installation (including any connected infrastructure)
Field PIERCE
Latitude 57° 9' 38.0'' N
Longitude 2° 17' 35.0'' E
Quadrant / block no. 23 / 22

Chemical 1

Chemical product released EMBR43442A
Total quantity of chemical released 5.0 kg

Formal investigation

Formal investigation ever opened No

Close off details

Release ever ongoing No

Source details

Source Chemical Injection - Valve Failure