IRS/2025/6167/PON1
Notification details
| Status | Completed |
|---|---|
| First observed date | 03 May 2025 |
| First observed time | 00:00 |
| Incident type(s) | Chemical release |
| Organisations involved | CNR INTERNATIONAL (U.K.) LIMITED |
| Installation | Ninian Southern Platform |
| Installation type | Production installation (including any connected infrastructure) |
| Field | LYELL |
| Latitude | 60° 48' 20.02'' N |
| Longitude | 1° 27' 1.36'' E |
| Quadrant / block no. | 3 / 2 |
Chemical 1
| Chemical product released | Oceanic HW540 E |
|---|---|
| Total quantity of chemical released | 71.74 kg |
Formal investigation
| Formal investigation ever opened | No |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Hydraulics - Open System - SCM Failure (Otherwise Unspecified) |
|---|