IRS/2025/6333/PON1

Notification details

Status Completed
First observed date 20 June 2025
First observed time 16:30
Incident type(s) Oil release
Organisations involved SPIRIT ENERGY PRODUCTION UK LIMITED
Installation CPC1
Installation type Production installation (including any connected infrastructure)
Field SOUTH MORECAMBE
Latitude 53° 50' 47.52'' N
Longitude 3° 34' 55.01'' W
Quadrant / block no. 110 / 8

Oil release details

Oil product released Diesel
How was the quantity released determined Estimated using Bonn Agreement Code
Total quantity of oil released 0.00063342 tonnes

Formal investigation

Formal investigation ever opened No

Close off details

Release ever ongoing No

Source details

Source Cranes - Diesel System