Back

IRS/2024/4110/PON10

Notification details

Status Completed
First observed date 24 February 2024
First observed time 01:00
Organisation involved SPIRIT ENERGY PRODUCTION UK LIMITED
Installation Morecambe South DP8 Platform
Field SOUTH MORECAMBE
Latitude 53° 53' 33.0'' N
Longitude 3° 37' 27.0'' W
Quadrant / block no. 110 / 02

Breached conditions details

Related to a breach of a condition of an approved Consent to Locate Yes
Breach related to Consent Condition and Marking Schedule Condition
Breached conditions 5. During the Works, A 4. Fogs

Fogs breached conditions

One or both signal failed Yes

Formal investigation

Formal investigation ever opened No

Further details

Installation fully compliant with its Consent to Locate conditions Yes
Non-compliance reasons related to Fog Signals
Loss of power No