IRS/2024/4126/PON10
Notification details
Status | Completed |
---|---|
First observed date | 28 February 2024 |
First observed time | 14:00 |
Organisation involved | ENI UK LIMITED |
Installation | Douglas FPF Irish Sea Pioneer |
Field | DOUGLAS |
Latitude | 53° 32' 13.0'' N |
Longitude | 3° 34' 42.0'' W |
Quadrant / block no. | 110 / 13 |
Breached conditions details
Related to a breach of a condition of an approved Consent to Locate | Yes |
---|---|
Breach related to | Consent Condition and Marking Schedule Condition |
Breached conditions | 5. During the Works, A 3. Lights |
Lights breached conditions
Main lights were not in operation | Yes |
---|---|
Subsidiary lights were not in operation | Yes |
Formal investigation
Formal investigation ever opened | No |
---|
Further details
Installation fully compliant with its Consent to Locate conditions | Yes |
---|---|
Non-compliance reasons related to | In combined ops nav lights were not syncronised |
Loss of power | No |