IRS/2024/5193/PON10
Notification details
| Status | In review |
|---|---|
| First observed date | 21 October 2024 |
| First observed time | 21:00 |
| Organisation involved | SPIRIT ENERGY NORTH SEA LIMITED |
| Installation | Chiswick Platform |
| Field | MARKHAM |
| Latitude | 53° 56' 23.882'' N |
| Longitude | 2° 44' 49.676'' E |
| Quadrant / block no. | 49 / 4 |
Breached conditions details
| Related to a breach of a condition of an approved Consent to Locate | Yes |
|---|---|
| Breach related to | Consent Condition and Marking Schedule Condition |
| Breached conditions | 5. During the Works, A 1. General |
Formal investigation
| Formal investigation ever opened | No |
|---|
Further details
| Loss of power | Yes, primary only |
|---|