IRS/2025/6323/PON10
Notification details
Status | Completed |
---|---|
First observed date | 17 June 2025 |
First observed time | 00:40 |
Organisation involved | SHELL U.K. LIMITED |
Installation | Brigantine BG |
Field | BRIGANTINE |
Latitude | 53° 24' 6.0'' N |
Longitude | 2° 39' 18.0'' E |
Quadrant / block no. | 49 / 19 |
Breached conditions details
Related to a breach of a condition of an approved Consent to Locate | Yes |
---|---|
Breach related to | Consent Condition and Marking Schedule Condition |
Breached conditions | 5. During the Works, A 3. Lights |
Lights breached conditions
Primary white lights lost | Yes |
---|
Formal investigation
Formal investigation ever opened | No |
---|
Further details
Installation fully compliant with its Consent to Locate conditions | Yes |
---|---|
Non-compliance reasons related to | Primary Power Supply |
Loss of power | Yes, primary only |
Loss of power date | 17 June 2025 |
Loss of power time | 00:40 |