IRS/2025/6868/PON10
Notification details
| Status | Completed |
|---|---|
| First observed date | 20 October 2025 |
| First observed time | 11:05 |
| Organisation involved | SPIRIT ENERGY RESOURCES LIMITED |
| Installation | Grove Wellhead Platform |
| Field | GROVE |
| Latitude | 53° 43' 0.0'' N |
| Longitude | 2° 51' 18.0'' E |
| Quadrant / block no. | 49 / 10 |
Breached conditions details
| Related to a breach of a condition of an approved Consent to Locate | Yes |
|---|---|
| Breach related to | Consent Condition and Marking Schedule Condition |
| Breached conditions | 5. During the Works, 1. Consent Validity, 2. Description of Works, 3. Location of Works, 4. Commencement of Works, 6. Cessation of Works, 7. Inspections, 8. Consent review, 9. Consent variation, 10. Consent non-compliance, A 1. General, A 3. Lights, A 2. Radio/Radar |
Lights breached conditions
| Primary white lights lost | Yes |
|---|
Formal investigation
| Formal investigation ever opened | No |
|---|
Further details
| Installation fully compliant with its Consent to Locate conditions | Yes |
|---|---|
| Non-compliance reasons related to | Primary Power Supply |
| Loss of power | Yes, primary only |
| Loss of power date | 20 October 2025 |
| Loss of power time | 11:05 |