Back

IRS/2026/7263/PON10

Notification details

Status Completed
First observed date 02 February 2026
First observed time 10:36
Organisation involved DUNLIN MANAGEMENT LIMITED
Installation Dunlin A Platform
Field DUNLIN
Latitude 61° 16' 30.0'' N
Longitude 1° 35' 51.0'' E
Quadrant / block no. 211 / 23

Breached conditions details

Related to a breach of a condition of an approved Consent to Locate Yes
Breach related to Consent Condition and Marking Schedule Condition
Breached conditions 5. During the Works, A 1. General, A 3. Lights

Lights breached conditions

Primary white lights lost Yes
Secondary white lights lost Yes

Formal investigation

Formal investigation ever opened No

Further details

Installation fully compliant with its Consent to Locate conditions Yes
Non-compliance reasons related to Primary Power Supply
Loss of power Yes, primary only
Loss of power date 02 February 2026
Loss of power time 10:36