PON1/2270
Notification details
| Status | Completed |
|---|---|
| First observed date | 03 September 2013 |
| First observed time | 15:15 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Arbroath Platform |
| Installation type | Fixed |
| Field | ARBROATH |
| Latitude | 57° 22' 29.084'' N |
| Longitude | 1° 22' 59.036'' E |
| Quadrant / block no. | 22 / 17 |
Chemical 1
| Chemical product released | Water Based Mud |
|---|---|
| Total quantity of chemical released | 3066.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Release of water based mud from overshot packer during pressure testing. |
|---|