PON1/2352
Notification details
| Status | Completed |
|---|---|
| First observed date | 06 October 2013 |
| First observed time | 16:45 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Ninian Central Platform |
| Installation type | Fixed |
| Field | |
| Latitude | 60° 51' 24.0'' N |
| Longitude | 1° 28' 9.0'' E |
| Quadrant / block no. | 3 / 3 |
Chemical 1
| Chemical product released | CALCIUM CHLORIDE BRINE |
|---|---|
| Total quantity of chemical released | 25.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Breakaway coupling failure during brine bunkering operation |
|---|