PON1/2455
Notification details
| Status | Completed |
|---|---|
| First observed date | 10 August 2013 |
| First observed time | 15:20 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Murdoch |
| Installation type | Other |
| Field | Rita |
| Latitude | 54° 14' 17.463'' N |
| Longitude | 2° 23' 23.2'' E |
| Quadrant / block no. | 44 / 22 |
Chemical 1
| Chemical product released | AQUALINK 300E VER2 |
|---|---|
| Total quantity of chemical released | 620.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Failure of the subsea hose on Hydraulic circuit - line isolated and subsea termination unit replaced |
|---|