Back

PON1/2044

Notification details

Status Completed
First observed date 09 July 2013
First observed time 10:45
Incident type(s) Chemical release
Organisations involved Talisman Sinopec Energy UK Limited
Installation Claymore A Platform
Installation type Fixed
Field CLAYMORE
Latitude 58° 26' 57.545'' N
Longitude 0° 15' 12.985'' W
Quadrant / block no. 14 / 19

Chemical 1

Chemical product released OSW85797
Total quantity of chemical released 0.001 kg

Formal investigation

Formal investigation ever opened Yes

Close off details

Release ever ongoing No

Source details

Source Block valve body failure on the Claymore water injection system