PON1/2111
Notification details
Status | Completed |
---|---|
First observed date | 27 July 2013 |
First observed time | 16:30 |
Incident type(s) | Chemical release |
Organisations involved | |
Installation | Britannia Platform |
Installation type | Fixed |
Field | Britannia |
Latitude | 58° 2' 55.13'' N |
Longitude | 1° 8' 19.54'' E |
Quadrant / block no. | 16 / 26 |
Chemical 1
Chemical product released | Castrol Transaqua HT2 |
---|---|
Total quantity of chemical released | 50.0 kg |
Formal investigation
Formal investigation ever opened | Yes |
---|
Close off details
Release ever ongoing | No |
---|
Source details
Source | Production wing valve spring actuator |
---|