PON1/3526
Notification details
| Status | Completed |
|---|---|
| First observed date | 28 October 2014 |
| First observed time | 18:00 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Cormorant North Platform |
| Installation type | Fixed |
| Field | CORMORANT NORTH |
| Latitude | 61° 14' 26.0'' N |
| Longitude | 1° 8' 58.0'' E |
| Quadrant / block no. | 211 / 21 |
Chemical 1
| Chemical product released | DMO86917 |
|---|---|
| Total quantity of chemical released | 611.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Demulsifier Tank Overfilled Into Disconnected Pipework |
|---|