PON1/3935
Notification details
| Status | Completed |
|---|---|
| First observed date | 31 March 2015 |
| First observed time | 19:40 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Hans Deul |
| Installation type | Mobile |
| Field | Shearwater |
| Latitude | 57° 1' 56.0'' N |
| Longitude | 1° 57' 18.0'' E |
Chemical 1
| Chemical product released | Oilbase mud |
|---|---|
| Total quantity of chemical released | 25.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Temporary Equipment - Failure of Equipment |
|---|