Back

PON1/4610

Notification details

Status Completed
First observed date 16 October 2015
First observed time 06:30
Incident type(s) Chemical release
Organisations involved Nexen Petroleum U.K. Limited
Installation Scott JD Platform
Installation type Fixed
Field SCOTT
Latitude 58° 17' 21.0'' N
Longitude 0° 12' 8.0'' E
Quadrant / block no. 15 / 22

Chemical 1

Chemical product released Ammonium Bisulphite 65%
Total quantity of chemical released 1.323 kg

Chemical 2

Chemical product released FOAMTREAT 943
Total quantity of chemical released 0.188 kg

Chemical 3

Chemical product released OS15
Total quantity of chemical released 0.021 kg

Formal investigation

Formal investigation ever opened Yes

Close off details

Release ever ongoing No

Source details

Source Subsea Chemical Systems - Fittings / Connections