PON1/5002
Notification details
| Status | Completed |
|---|---|
| First observed date | 18 March 2016 |
| First observed time | 15:00 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Fionn Subsea Tieback |
| Installation type | Fixed |
| Field | FIONN |
| Latitude | 61° 14' 29.09'' N |
| Longitude | 1° 22' 9.91'' E |
Chemical 1
| Chemical product released | Castrol Transaqua HT2 |
|---|---|
| Total quantity of chemical released | 75.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Hydraulics - Open System - Solenoid Failure |
|---|