Notification details
| Status | Completed |
|---|---|
| First observed date | 08 August 2017 |
| First observed time | 10:10 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Pickerill A Platform |
| Installation type | Fixed |
| Field | PICKERILL |
| Latitude | 53° 31' 30.0'' N |
| Longitude | 1° 9' 38.0'' E |
| Quadrant / block no. | 48 / 11 |
Chemical 1
| Chemical product released | Houton Aqualink HT804F |
|---|---|
| Total quantity of chemical released | 500.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Hydraulic Manifold/Control Panel - Small Bore Fittings |
|---|