PON1/6772
Notification details
| Status | Completed |
|---|---|
| First observed date | 29 August 2017 |
| First observed time | 09:00 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Piper B Platform |
| Installation type | Fixed |
| Field | Piper |
| Latitude | 58° 27' 40.009'' N |
| Longitude | 0° 15' 3.008'' E |
| Quadrant / block no. | 15 / 17 |
Chemical 1
| Chemical product released | Pelagic 100 Production Control Fluid |
|---|---|
| Total quantity of chemical released | 22305.0 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | Yes |
|---|
Source details
| Source | Hydraulics - Closed system - Valve Failure |
|---|