PON1/6833
Notification details
| Status | Completed |
|---|---|
| First observed date | 26 October 2017 |
| First observed time | 18:00 |
| Incident type(s) | Chemical release |
| Organisations involved | |
| Installation | Balmoral FPV |
| Installation type | Fixed |
| Field | BALMORAL |
| Latitude | 58° 13' 42.805'' N |
| Longitude | 1° 6' 25.121'' E |
| Quadrant / block no. | 16 / 21 |
Chemical 1
| Chemical product released | Pelagic 100 Production Control Fluid |
|---|---|
| Total quantity of chemical released | 8494.8 kg |
Formal investigation
| Formal investigation ever opened | Yes |
|---|
Close off details
| Release ever ongoing | No |
|---|
Source details
| Source | Hydraulics - Open System - SCM Failure (Otherwise unspecified) |
|---|