PON1/7327
Notification details
| Status | Completed | 
|---|---|
| First observed date | 07 May 2018 | 
| First observed time | 14:00 | 
| Incident type(s) | Chemical release | 
| Organisations involved | |
| Installation | Claymore A Platform | 
| Installation type | Fixed | 
| Field | Scapa | 
| Latitude | 58° 26' 58.0'' N | 
| Longitude | 0° 15' 13.0'' E | 
| Quadrant / block no. | 14 / 19 | 
Chemical 1
| Chemical product released | PELAGIC 100 | 
|---|---|
| Total quantity of chemical released | 259.0 kg | 
Formal investigation
| Formal investigation ever opened | Yes | 
|---|
Close off details
| Release ever ongoing | No | 
|---|
Source details
| Source | Hydraulics - Closed system - Fittings / Connections | 
|---|