PON1/9020
Notification details
Status | Completed |
---|---|
First observed date | 02 November 2019 |
First observed time | 22:40 |
Incident type(s) | Chemical release |
Organisations involved | |
Installation | Clyde Platform |
Installation type | Fixed |
Field | CLYDE |
Latitude | 56° 27' 10.0'' N |
Longitude | 2° 17' 18.0'' E |
Quadrant / block no. | 30 / 17 |
Chemical 1
Chemical product released | METHANOL (all dilutions) |
---|---|
Total quantity of chemical released | 0.8 kg |
Formal investigation
Formal investigation ever opened | Yes |
---|
Close off details
Release ever ongoing | No |
---|
Source details
Source | Chemical Injection - Valve Failure |
---|