PON1/9638
Notification details
Status | Completed |
---|---|
First observed date | 26 July 2020 |
First observed time | 16:00 |
Incident type(s) | Chemical release |
Organisations involved | |
Installation | Brae A Platform |
Installation type | Fixed |
Field | BRAE-SOUTH [Part of BRAE] |
Latitude | 58° 41' 34.076'' N |
Longitude | 1° 16' 53.206'' E |
Quadrant / block no. | 16 / 7 |
Chemical 1
Chemical product released | CRW85733 |
---|---|
Total quantity of chemical released | 3.63 kg |
Chemical 2
Chemical product released | GT-7510 |
---|---|
Total quantity of chemical released | 454.0 kg |
Chemical 3
Chemical product released | Proxel XL2 |
---|---|
Total quantity of chemical released | 4.75 kg |
Formal investigation
Formal investigation ever opened | Yes |
---|
Close off details
Release ever ongoing | No |
---|
Source details
Source | Fixed Chemical Pipework (Utility Chemicals) - Pinhole Leak |
---|