IRS/2022/1592/PON10

Notification details

Status Completed
First observed date 05 August 2022
First observed time 12:15
Organisation involved SPIRIT ENERGY PRODUCTION UK LIMITED
Installation Morecambe South DP4 Platform
Field SOUTH MORECAMBE
Latitude 53° 52' 30.0'' N
Longitude 3° 33' 39.0'' W
Quadrant / block no. 110 / 03

Breached conditions details

Related to a breach of a condition of an approved Consent to Locate Yes
Breach related to Consent Condition and Marking Schedule Condition
Breached conditions 5. During the Works, A 3. Lights

Lights breached conditions

Primary white lights lost Yes

Formal investigation

Formal investigation ever opened No

Further details

Installation fully compliant with its Consent to Locate conditions Yes
Non-compliance reasons related to Mooring and Buoys
Loss of power No